AS ON 01.04.2024
CLUSTER - 01 (BUNGALOW HOUSE NO. 01 - 08)
Ground floor slab completed, 1st floor slab reinforcement & shuttering work in progress.
CLUSTER - 02 (BUNGALOW HOUSE NO. 09 - 14)
Foundation work in progress.
CLUSTER - 05 (BUNGALOW HOUSE NO. 32 - 34)
Above roof work and brick work is in progress.
CLUSTER - 06 (BUNGALOW HOUSE NO. 45 - 51)
Above roof work and brick work is in progress.
VILLAMENT 17 & 18
2nd floor slab casting completed, 3rd floor slab reinforcement & shuttering work is in progress.
VILLAMENT 23
Roof slab reinforcement & shuttering work is in progress.
VILLAMENT 24
Roof slab reinforcement & shuttering work is in progress.
VILLAMENT 25
Roof slab reinforcement & shuttering work is in progress.
VILLAMENT 26
Roof slab reinforcement & shuttering work is in progress.
VILLAMENT 27
Roof slab reinforcement & shuttering work is in progress.
APARTMENT (Tower 12)
Foundation work (pile cap) is in progress.
APARTMENT (Tower 13)
Foundation work (pile cap) is in progress.
APARTMENT (Tower 14)
Piling work completed, soil dressing work is in progress.
APARTMENT (Tower 15)
Piling work in progress.
APARTMENT (Tower 16)
Piling work completed, soil dressing work is in progress.