AS ON 01.07.2026

    CLUSTER - 01 (BUNGALOW HOUSE NO. 01 - 08)
  • Finishing work nearly completed.
  • Sanitary Fitting work in progress (Deep cleaning work in progress)
    CLUSTER - 02 (BUNGALOW HOUSE NO. 09 - 14)
  • Finishing work nearly completed.
  • Sanitary Fitting work in progress (Deep cleaning work in progress)
    CLUSTER - 04 (BUNGALOW HOUSE NO. 27 - 29)
  • Tiles work yet to start.
    CLUSTER - 05 (BUNGALOW HOUSE NO. 30 - 31)
  • Flooring work done.
  • Railing work pending.Finishing Work in Progress.
    CLUSTER - 05 (BUNGALOW HOUSE NO.32 - 34)
  • Finishing work completed.
    CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
  • Aluminum Work is in Progress.
    CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 45)
  • Finishing work is completed
    CLUSTER - 06 (BUNGALOW HOUSE NO. 46 - 51)
  • Finishing work nearly completed.
    CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
  • Flooring work is in progress.(Excluding 52,53)
    CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
  • Flooring work is in progress.
    VILLAMENT (TOWN HOUSE NO. 01 - 04)
  • In Town house (1-2) 1st floor level slab casting done
  • 1st to 2nd floor column work in progress.
  • Town house (3-4) 1stfloor level slab completed .
  • 1st to 2nd column work in progress.
    VILLAMENT (TOWN HOUSE NO. 05 - 07)
  • 2nd floorlevel slab completed
  • 3rd floor level slab shuttering work in progress.
    VILLAMENT (TOWN HOUSE NO. 15 - 16)
  • Piling work completed.
    VILLAMENT (TOWN HOUSE NO. 17)
  • Finishing work is in progress.
  • Flooring work has yet to start.
    VILLAMENT (TOWN HOUSE NO. 18)
  • Finishing work completed.
    VILLAMENT (TOWN HOUSE NO. 19 - 20)
  • In Town house 19,2ndfloor level slabcasting completed.
  • In Town House no. 20 1st floor slab in progress.
  • 2nd to 3rd floor Lift wall WIP.
  • Town house 20, 2nd floor levelslab completed.
  • 2nd to 3rd Column WIP.
    VILLAMENT (TOWN HOUSE NO. 21 - 22)
  • Ground floor slab castingwork completed.
  • 1st Floor to 2nd floor Column work in progress.
    VILLAMENT (TOWN HOUSE NO. 23 - 27)
  • Flooring, POP, Door fixing work in progress.
    APARTMENT - (Tower 12)
  • Super-structure work in progress i.e. 15th floor slab work Completed
  • 16th floor slab work in progress.
    APARTMENT - (Tower 13)
  • Super-structure work in progress i.e.18thfloor slab work completed
  • Swimming pool work in progress.
  • 19th floor column work in progress.
    APARTMENT (Tower 14)
  • Super-structure work in progress i.e. 8th slab work in progress.
  • Swimming pool work in progress.
    APARTMENT (Tower 15)
  • Super-structure work in progress i.e. 6th slab work partially completed.
  • Swimming pool work in progress.
    APARTMENT (Tower 16)
  • Super-structure work in progress i.e.6th Column work in progress.
  • Ramp 2nd to 3rd Shuttering work in progress.
    APARTMENT (Tower 19)
  • Super-structure work in progress i.e. 4th Floor Slab Work in progress.
    APARTMENT (Tower 20)
  • Sub-structure work in progress i.e.Tie beamwork in progress.
    TEMPLE
  • Civil Work Completed.
  • External plaster work in progress.
    PRIMUS GANGES (SENIOR LIVING)
  • Pilling work completed.
  • Foundation work in progress.
    NOTE:
  • Infrastructure development, External Plumbing, Cable Trench, UGR, STP, Road and Land development work are also in progress at different parts of project.