Sanitary Fitting work in progress (Deep cleaning work in progress)
CLUSTER - 02 (BUNGALOW HOUSE NO. 09 - 14)
Finishing work nearly completed.
Sanitary Fitting work in progress (Deep cleaning work in progress)
CLUSTER - 04 (BUNGALOW HOUSE NO. 27 - 29)
Tiles work yet to start.
CLUSTER - 05 (BUNGALOW HOUSE NO. 30 - 31)
Flooring work done.
Railing work pending.Finishing Work in Progress.
CLUSTER - 05 (BUNGALOW HOUSE NO.32 - 34)
Finishing work completed.
CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
Aluminum Work is in Progress.
CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 45)
Finishing work is completed
CLUSTER - 06 (BUNGALOW HOUSE NO. 46 - 51)
Finishing work nearly completed.
CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
Flooring work is in progress.(Excluding 52,53)
CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
Flooring work is in progress.
VILLAMENT (TOWN HOUSE NO. 01 - 04)
In Town house (1-2) 1st floor level slab casting done
1st to 2nd floor column work in progress.
Town house (3-4) 1stfloor level slab completed .
1st to 2nd column work in progress.
VILLAMENT (TOWN HOUSE NO. 05 - 07)
2nd floorlevel slab completed
3rd floor level slab shuttering work in progress.
VILLAMENT (TOWN HOUSE NO. 15 - 16)
Piling work completed.
VILLAMENT (TOWN HOUSE NO. 17)
Finishing work is in progress.
Flooring work has yet to start.
VILLAMENT (TOWN HOUSE NO. 18)
Finishing work completed.
VILLAMENT (TOWN HOUSE NO. 19 - 20)
In Town house 19,2ndfloor level slabcasting completed.
In Town House no. 20 1st floor slab in progress.
2nd to 3rd floor Lift wall WIP.
Town house 20, 2nd floor levelslab completed.
2nd to 3rd Column WIP.
VILLAMENT (TOWN HOUSE NO. 21 - 22)
Ground floor slab castingwork completed.
1st Floor to 2nd floor Column work in progress.
VILLAMENT (TOWN HOUSE NO. 23 - 27)
Flooring, POP, Door fixing work in progress.
APARTMENT - (Tower 12)
Super-structure work in progress i.e. 15th floor slab work Completed
16th floor slab work in progress.
APARTMENT - (Tower 13)
Super-structure work in progress i.e.18thfloor slab work completed
Swimming pool work in progress.
19th floor column work in progress.
APARTMENT (Tower 14)
Super-structure work in progress i.e. 8th slab work in progress.
Swimming pool work in progress.
APARTMENT (Tower 15)
Super-structure work in progress i.e. 6th slab work partially completed.
Swimming pool work in progress.
APARTMENT (Tower 16)
Super-structure work in progress i.e.6th Column work in progress.
Ramp 2nd to 3rd Shuttering work in progress.
APARTMENT (Tower 19)
Super-structure work in progress i.e. 4th Floor Slab Work in progress.
APARTMENT (Tower 20)
Sub-structure work in progress i.e.Tie beamwork in progress.
TEMPLE
Civil Work Completed.
External plaster work in progress.
PRIMUS GANGES (SENIOR LIVING)
Pilling work completed.
Foundation work in progress.
NOTE:
Infrastructure development, External Plumbing, Cable Trench, UGR, STP, Road and Land development work are also in progress at different parts of project.