AS ON 01.04.2025

    CLUSTER - 01 (BUNGALOW HOUSE NO. 01 - 08)
  • Brick work, plastering and mep work is in progress.
    CLUSTER - 02 (BUNGALOW HOUSE NO. 09 - 14)
  • Brick work and mep work is in progress.
    CLUSTER - 04 (BUNGALOW HOUSE NO. 27 - 29)
  • Superstructure work in progress (column up to 1st floor work in progress).
    CLUSTER - 05 (BUNGALOW HOUSE NO. 30 - 31)
  • Superstructure work in progress
  • 1st slab completed (column up to 2nd floor, work in progress).
    CLUSTER - 05 (BUNGALOW HOUSE NO. 32 - 33)
  • Finishing work completed.
    CLUSTER - 05 (BUNGALOW HOUSE NO. 34)
  • Finishing work in progress.
    CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
  • 1st slab casting work has been completed from Row house (35-39)
  • Column upto 1 st floor work in progress from Row house (40-41).
    CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 44)
  • Superstructure work in progress.
  • 1st slab completed (column up to 2nd floor work in progress).
    CLUSTER - 06 (BUNGALOW HOUSE NO. 45 - 51)
  • Plastering and mep work is in progress.
    CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
  • Superstructure work in progress (column up to 1 st floor work in progress).
    CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
  • Superstructure work in progress (column up to 1 st floor work in progress).
    VILLAMENT (TOWN HOUSE NO. 01 - 07)
  • Piling work completed.
  • Excavation work started foundation work will start soon.
    VILLAMENT (TOWN HOUSE NO. 17)
  • Finishing work is in progress.
    VILLAMENT (TOWN HOUSE NO. 18)
  • Finishing work completed.
    VILLAMENT (TOWN HOUSE NO. 19 - 22)
  • Foundation work is in progress.
    VILLAMENT (TOWN HOUSE NO. 23 - 27)
  • Plastering work and mep work is in progress.
  • Finishing work will start soon.
    APARTMENT - (Tower 12)
  • Super-structure work in progress i.e. 4th floor slab work partially completed, 5 th floor slab work in progress.
    APARTMENT - (Tower 13)
  • Super-structure work i.e. 4th floor slab work completed.
    APARTMENT (Tower 14)
  • Super-structure work in progress i.e. 1st floor slab completed, 2nd floor slab work in progress.
    APARTMENT (Tower 15)
  • Super-structure work in progress i.e. 1st floor slab work in progress.
    APARTMENT (Tower 16)
  • Shear wall/column up to 1 st floor level in progress.
    APARTMENT (Tower 19)
  • Foundation work in progress.
    NOTE:
  • Infrastructure development STP, Road and Land development work are also in progress at different parts of the project.