AS ON 01.01.2026

    CLUSTER - 01 (BUNGALOW HOUSE NO. 01 - 08)
  • Finishing work in progress.
    CLUSTER - 02 (BUNGALOW HOUSE NO. 09 - 14)
  • Finishing work in progress.
    CLUSTER - 04 (BUNGALOW HOUSE NO. 27 - 29)
  • Brickwork is in progress..
    CLUSTER - 05 (BUNGALOW HOUSE NO. 30 - 31)
  • Plastering work is in progress.
    CLUSTER - 05 (BUNGALOW HOUSE NO.32 - 34)
  • Finishing work completed.
    CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
  • Plastering work is in progress.
    CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 45)
  • Finishing work is in progress.
    CLUSTER - 06 (BUNGALOW HOUSE NO. 46 - 51)
  • Finishing work in progress.
    CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
  • Brickwork & plastering work is in progress.
    CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
  • Brickwork & plastering work is in progress.
    VILLAMENT (TOWN HOUSE NO. 01 - 04)
  • Foundation work in progress.
    VILLAMENT (TOWN HOUSE NO. 05 - 07)
  • Tie beam work in progress.
    VILLAMENT (TOWN HOUSE NO. 17)
  • Finishing work is in progress.
    VILLAMENT (TOWN HOUSE NO. 18)
  • Finishing work completed.
    VILLAMENT (TOWN HOUSE NO. 19 - 20)
  • Super-structure work in progress i.e. 1st slab work in progress.
    VILLAMENT (TOWN HOUSE NO. 21 - 22)
  • Plinth work is in progress.
    VILLAMENT (TOWN HOUSE NO. 23 - 27)
  • Finishing work in progress.
    APARTMENT - (Tower 12)
  • Super-structure work in progress i.e. 7th slab workin progress.
    APARTMENT - (Tower 13)
  • Super-structure work in progress i.e.9th slab work completed & swimming pool slab in progress.
    APARTMENT (Tower 14)
  • Super-structure work in progress i.e. 6th slab work in progress& swimming pool slab in progress.
    APARTMENT (Tower 15)
  • Super-structure work in progress i.e. 4th slab in progress& swimming pool slab in progress.
    APARTMENT (Tower 16)
  • Super-structure work in progress i.e. 2nd slabwork partially completed, 3rd slab work in progress.
    APARTMENT (Tower 19)
  • Super-structure work in progress i.e. 1st slab work in progress.
    APARTMENT (Tower 20)
  • Piling work completed, excavation work in progress.
    TEMPLE
  • Piling completed, foundation work in progress.
    NOTE:
  • Infrastructure development, External Plumbing, Cable Trench, UGR, STP, Road and Land development work are also in progress at different part of project.