Roof slab casting completed & brickwork is in progress.
CLUSTER - 05 (BUNGALOW HOUSE NO. 32 - 33)
Finishing work completed.
CLUSTER - 05 (BUNGALOW HOUSE NO. 34)
Finishing work in progress.
CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
Roof slab casting completed & brickwork is in progress.
CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 44)
Roof slab casting completed & brickwork is in progress.
CLUSTER - 06 (BUNGALOW HOUSE NO. 45 - 51)
Finishing work in progress.
CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
Superstructure work in progress, (roof slab work in progress &brickwork is in progress).
CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
Roof slab casting completed & brickwork is in progress.
VILLAMENT (TOWN HOUSE NO. 01 - 07)
Piling work completed, foundation work started from Villaments (1-4).
VILLAMENT (TOWN HOUSE NO. 17)
Finishing work is in progress.
VILLAMENT (TOWN HOUSE NO. 18)
Finishing work completed.
VILLAMENT (TOWN HOUSE NO. 19 - 20)
Super-structure work in progress i.e. 1st slab work in progress.
VILLAMENT (TOWN HOUSE NO. 21 - 22)
Foundation work is in progress.
VILLAMENT (TOWN HOUSE NO. 23 - 27)
Finishing work in progress.
APARTMENT - (Tower 12)
Super-structure work in progress i.e. 6th slab work partially completed, 7th slab workin progress.
APARTMENT - (Tower 13)
Super-structure work in progress i.e.7th slab work completed.
APARTMENT (Tower 14)
Super-structure work in progressi.e. 4th slab work completed &5th/6th slab work in progress.
APARTMENT (Tower 15)
Super-structure work in progress i.e. 3rd slab work completed.
APARTMENT (Tower 16)
Super-structure work in progress i.e. 1st slab work partially completed & 2nd slab work in progress.
APARTMENT (Tower 18)
Piling work is in progress.
APARTMENT (Tower 19)
Foundation work completed, shear wall/column up to 1st floor in progress.
APARTMENT (Tower 20)
Piling work is in progress.
TEMPLE
Piling completed, foundation work in progress.
PRIMUS GANGES (SENIOR LIVING)
Piling completed, foundation work in progress.
NOTE:
Infrastructure development, External Plumbing, Cable Trench, UGR, STP, Road and Land development work are also in progress at different part of project.