AS ON 01.04.2025
CLUSTER - 01 (BUNGALOW HOUSE NO. 01 - 08)
Brick work, plastering and mep work is in progress.
CLUSTER - 02 (BUNGALOW HOUSE NO. 09 - 14)
Brick work and mep work is in progress.
CLUSTER - 04 (BUNGALOW HOUSE NO. 27 - 29)
Superstructure work in progress (column up to 1st floor work in progress).
CLUSTER - 05 (BUNGALOW HOUSE NO. 30 - 31)
Superstructure work in progress
1st slab completed (column up to 2nd floor, work in progress).
CLUSTER - 05 (BUNGALOW HOUSE NO. 32 - 33)
Finishing work completed.
CLUSTER - 05 (BUNGALOW HOUSE NO. 34)
Finishing work in progress.
CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
1st slab casting work has been completed from Row house (35-39)
Column upto 1 st floor work in progress from Row house (40-41).
CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 44)
Superstructure work in progress.
1st slab completed (column up to 2nd floor work in progress).
CLUSTER - 06 (BUNGALOW HOUSE NO. 45 - 51)
Plastering and mep work is in progress.
CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
Superstructure work in progress (column up to 1 st floor work in progress).
CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
Superstructure work in progress (column up to 1 st floor work in progress).
VILLAMENT (TOWN HOUSE NO. 01 - 07)
Piling work completed.
Excavation work started foundation work will start soon.
VILLAMENT (TOWN HOUSE NO. 17)
Finishing work is in progress.
VILLAMENT (TOWN HOUSE NO. 18)
Finishing work completed.
VILLAMENT (TOWN HOUSE NO. 19 - 22)
Foundation work is in progress.
VILLAMENT (TOWN HOUSE NO. 23 - 27)
Plastering work and mep work is in progress.
Finishing work will start soon.
APARTMENT - (Tower 12)
Super-structure work in progress i.e. 4th floor slab work partially completed, 5 th floor slab work in progress.
APARTMENT - (Tower 13)
Super-structure work i.e. 4th floor slab work completed.
APARTMENT (Tower 14)
Super-structure work in progress i.e. 1st floor slab completed, 2nd floor slab work in progress.
APARTMENT (Tower 15)
Super-structure work in progress i.e. 1st floor slab work in progress.
APARTMENT (Tower 16)
Shear wall/column up to 1 st floor level in progress.
APARTMENT (Tower 19)
Foundation work in progress.
NOTE:
Infrastructure development STP, Road and Land development work are also in progress at different parts of the project.