CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
Plastering work is in progress.
CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 45)
Finishing work is in progress.
CLUSTER - 06 (BUNGALOW HOUSE NO. 46 - 51)
Finishing work in progress.
CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
Brickwork & plastering work is in progress.
CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
Brickwork & plastering work is in progress.
VILLAMENT (TOWN HOUSE NO. 01 - 04)
Foundation work in progress.
VILLAMENT (TOWN HOUSE NO. 05 - 07)
Tie beam work in progress.
VILLAMENT (TOWN HOUSE NO. 17)
Finishing work is in progress.
VILLAMENT (TOWN HOUSE NO. 18)
Finishing work completed.
VILLAMENT (TOWN HOUSE NO. 19 - 20)
Super-structure work in progress i.e. 1st slab work in progress.
VILLAMENT (TOWN HOUSE NO. 21 - 22)
Plinth work is in progress.
VILLAMENT (TOWN HOUSE NO. 23 - 27)
Finishing work in progress.
APARTMENT - (Tower 12)
Super-structure work in progress i.e. 7th slab workin progress.
APARTMENT - (Tower 13)
Super-structure work in progress i.e.9th slab work completed & swimming pool slab in progress.
APARTMENT (Tower 14)
Super-structure work in progress i.e. 6th slab work in progress& swimming pool slab in progress.
APARTMENT (Tower 15)
Super-structure work in progress i.e. 4th slab in progress& swimming pool slab in progress.
APARTMENT (Tower 16)
Super-structure work in progress i.e. 2nd slabwork partially completed, 3rd slab work in progress.
APARTMENT (Tower 19)
Super-structure work in progress i.e. 1st slab work in progress.
APARTMENT (Tower 20)
Piling work completed, excavation work in progress.
TEMPLE
Piling completed, foundation work in progress.
NOTE:
Infrastructure development, External Plumbing, Cable Trench, UGR, STP, Road and Land development work are also in progress at different part of project.