AS ON 01.10.2025

    CLUSTER - 01 (BUNGALOW HOUSE NO. 01 - 08)
  • Finishing work in progress.
    CLUSTER - 02 (BUNGALOW HOUSE NO. 09 - 14)
  • Finishing work in progress.
    CLUSTER - 04 (BUNGALOW HOUSE NO. 27 - 29)
  • Roof slab casting completed.
  • Brickwork will start soon.
    CLUSTER - 05 (BUNGALOW HOUSE NO. 30 - 31)
  • Roof slab casting completed & brickwork is in progress.
    CLUSTER - 05 (BUNGALOW HOUSE NO. 32 - 33)
  • Finishing work completed.
    CLUSTER - 05 (BUNGALOW HOUSE NO. 34)
  • Finishing work in progress.
    CLUSTER - 05 (BUNGALOW HOUSE Phase II NO. 35 - 41)
  • Roof slab casting completed & brickwork is in progress.
    CLUSTER - 06 (BUNGALOW HOUSE NO. 42 - 44)
  • Roof slab casting completed & brickwork is in progress.
    CLUSTER - 06 (BUNGALOW HOUSE NO. 45 - 51)
  • Finishing work in progress.
    CLUSTER - 07 (BUNGALOW HOUSE NO. 52 - 57)
  • Superstructure work in progress, (roof slab work in progress &brickwork is in progress).
    CLUSTER - 08 (BUNGALOW HOUSE NO. 58 - 63)
  • Roof slab casting completed & brickwork is in progress.
    VILLAMENT (TOWN HOUSE NO. 01 - 07)
  • Piling work completed, foundation work started from Villaments (1-4).
    VILLAMENT (TOWN HOUSE NO. 17)
  • Finishing work is in progress.
    VILLAMENT (TOWN HOUSE NO. 18)
  • Finishing work completed.
    VILLAMENT (TOWN HOUSE NO. 19 - 20)
  • Super-structure work in progress i.e. 1st slab work in progress.
    VILLAMENT (TOWN HOUSE NO. 21 - 22)
  • Foundation work is in progress.
    VILLAMENT (TOWN HOUSE NO. 23 - 27)
  • Finishing work in progress.
    APARTMENT - (Tower 12)
  • Super-structure work in progress i.e. 6th slab work partially completed, 7th slab workin progress.
    APARTMENT - (Tower 13)
  • Super-structure work in progress i.e.7th slab work completed.
    APARTMENT (Tower 14)
  • Super-structure work in progressi.e. 4th slab work completed &5th/6th slab work in progress.
    APARTMENT (Tower 15)
  • Super-structure work in progress i.e. 3rd slab work completed.
    APARTMENT (Tower 16)
  • Super-structure work in progress i.e. 1st slab work partially completed & 2nd slab work in progress.
    APARTMENT (Tower 18)
  • Piling work is in progress.
    APARTMENT (Tower 19)
  • Foundation work completed, shear wall/column up to 1st floor in progress.
    APARTMENT (Tower 20)
  • Piling work is in progress.
    TEMPLE
  • Piling completed, foundation work in progress.
    PRIMUS GANGES (SENIOR LIVING)
  • Piling completed, foundation work in progress.
    NOTE:
  • Infrastructure development, External Plumbing, Cable Trench, UGR, STP, Road and Land development work are also in progress at different part of project.